Projects and Works

Introduction

The Capital Works Program has been developed to meet anticipated community infrastructure needs and the future development of the Town to align with the strategic plan, driven by population growth, requirements of the community and asset management.  These works include footpath replacement, traffic management treatments and road re-sheeting works among other minor capital works.

Jump to:

Major projects
Upcoming capital works
Underground power project
nbn
 rollout
Maintenance


Major projects

Claremont Aquatic Centre splash pad construction 

Work is underway to build our much-anticipated water playground in time for the busy summer season. The 47-year-old toddler pool is being replaced with interactive features including jet sprays; channels with pumps, wheels and gates; and a mega bucket water dump.

Freshwater Bay Museum redevelopment 

The Town of Claremont’s historic Freshwater Bay Museum site is being redeveloped to increase access to heritage, education and culture for our community. A steering group has been established to bring the $1.26 million project to build stage.

Claremont Train Station upgrade

The Public Transport Authority identified Claremont Train Station as the best location for trains to turn back towards Perth to support the Forrestfield-Airport Link.  The proposed project also includes a broader upgrade of the station's facilities. 

More information

For an overview of these major projects, please click here.

 

Upcoming capital works 

Roadworks - Anstey St (between Stirling Hwy and Bindaring Pde)

The road  rehabilitation project for Anstey Street between Stirling Highway and Bindaring Parade is scheduled to commence on Monday 14 October 2019.  The goal is to complete these works by Friday 25 October 2019, weather permitting.

If you have any queries regarding these works, please contact us.

Underground power project

Underground-Parking.jpg

The undergrounding of power to the final pocket of the Town of Claremont is nearing practical completion. Some reinstatement work for verges are still undergoing. 

Residents in the project area will be notified via written correspondence of the completion of works in their street.  

map.png

  Estimated Start Date Estimated Completion Date
Zone 1 May 2018 February 2019 (complete)
Zone 2 June 2018 May 2019 (complete)
Zone 3 June 2018 May 2019 (complete)
Zone 4 October 2018 June 2019 (complete)
Zone 5 November 2018 June 2019 (complete)
Zone 6 January 2019 June 2019 (complete)
Zone 7 February 2019 July 2019 (complete)
Zone 8 February 2019 July 2019 (complete)
Zone 9 August 2018 April 2019 (complete)
Project Completion   August 2019


Last updated 2 September 2019. 

Please click here to view the Frequently Asked Questions. 

To view a map of the high voltage transmission powerlines (66v and 132v) that will not be removed, please click here.

Maintenance

To report a problem

Roads signs line markings and traffic signals are serviced by Main Roads WA.